Title of Invention

EQUIPMENT AND METHOD FOR SERVICING A WIND TURBINE

Abstract Equipment for servicing a wind turbine after a hub (1) of the wind turbine has been mounted, said equipment comprising a crane (8) for lowering and hoisting wind turbine appliances from and to the hub (1), characterized in that connecting means (5, 6) are provided for primarily securing the equipment including the crane (8) to a curved surface (7) of the hub, and receiving the load of the crane thereon, the connecting means having a lower surface adapted to conform to the hub curved surface (7).
Full Text HELD OF THE INVENTION
The invention relates to a method for conducting service on a wind turbine after the wind
turbine is erected and after the hub of the wind turbine is mounted on the main shaft of
the wind turbine. The invention also relates to equipment for conducting such service and
furthermore the invention relates to a connecting piece and a crane constituting part of the
equipment. Finally, the invention relates to a wind turbine, to a hub and to uses of a hub.
BACKGROUND OF THE INVENTION
Although much of the appliances installed in a wind turbine is intended for lasting a very
long time, some of the appliances must be replaced or must be repaired during the service
life of the wind turbine. Equipment installed in the nacelle or in the tower of the wind
turbine may be removed from or lifted to the nacelle by means of cranes or other lifting
means provided on or in connection with the nacelle. The tower and the machine frame of
the nacelle are solid structures where even large cranes may be secured to and where
even heavy appliances may be lowered from or lifted to without any difficulties. However,
appliances installed in the hub, in connection with the wings or in connection with the hub
may be more difficult to access and to handle for possible removal in order for the
appliances to be replaced or be repaired at a more suited location than the service location
of the appliances. Often, a hatch is provided in the top of the nacelle housing, enabling
access from or to the outside of the hub and from or to the nacelle and further down or up
through the tower. This manner, in which appliances at the more remote locations
mentioned Is handled, is a secure manner, but also quite time-consuming. Also, during
handling through the hatch of the nacelle housing, the escape way from the remote
locations is blocked, endangering the working conditions at these remote locations.
SUMMARY OF THE INVENTION
It may be an object of the present invention to provide a method and equipment to be
used by the method, and which does not posses the above-mentioned disadvantages.


Accordingly, the present invention provides an equipment for servicing a wind turbine after a
hub of the wind turbine has been mounted, said equipment comprising a crane for lowering and
hoisting wind turbine appliances from and to the hub, characterized in that connecting means
are provided for primarily securing the equipment including the crane to a curved surface of the
hub, and receiving the load of the crane thereon, the connecting means having a lower surface
adapted to conform to the hub curved surface.
This object is obtained by a method comprising mounting of servicing equipment on the hub of
the wind turbine and lowering and hoisting wind turbine appliances from and to the hub.
Thereby, it is possible to lower from and to lift to the hub, the appliances which is to be
replaced or repaired without using the hatch constituting the escape way and without having to
transfer the appliances through the nacelle and along the tower.
In a preferred embodiment the servicing equipment is mounted to the outside surface of the hub,
and where the equipment to be lowered from and hoisted to the hub is lowered and hoisted to
the hub at a front of the hub. Even more preferred, the servicing equipment is mounted by
means of already available holes, said holes formerly used for hoisting the hub to the main shaft
of the wind turbine.
By securing the servicing equipment to the surface of the hub and by furthermore utilising
already available holes, it is very easy and fast to erect the servicing equipment and possible to
lower or to hoist any equipment from the hub, the blades or the spinner without having to access
the interior of the hub, i.e. all the already limited space inside the hub will not be occupied by
the servicing equipment according to the invention.
The present invention also provides a method of conducting service on a wind turbine, the
method involving the mounting of the equipment onto the curved surface of the wind turbine
hub by securing the connecting means to the hub curved surface, and employing the crane to
lower and hoist wind turbine appliances from and to the hub.

Accordingly, the object of the invention is also obtained by equipment being provided with
means for primarily securing the equipment to the hub opposite from securing the
equipment to the nacelle or other parts, different from the hub, of the wind turbine.
The previously mentioned advantages, which are obtained by the method according to the
invention, are fulfilled by means of the equipment according to the invention. Securing the
equipment primarily to the hub avoids obstructing the hatch in the top of the nacelle, and
makes it possible easily to handle appliances to. and from the hub, the blades and the hub.
BRIEF DESCRIPTION OF THE ACCOMPANYING DRAWINGS
In the following the wind turbine will be described with reference to the drawing, where
fig. 1 is a plane view of equipment according to the invention mounted onto the hub of a
wind turbine,
fig. 2 is a perspective view of a hub for a wind turbine and with coupling elements
mounted on the hub,
fig. 3 is one plane view of a hub for a wind turbine and with one coupling element mounted
on the hub,
fig. 4 is another plane view of a hub for a wind turbine and with one coupling element
mounted on the hub,
fig. 5 is a perspective view of part of a hub for a wind turbine and with one coupling
element mounted on the hub,


fig. 6 is a perspective view of a cross section of a hub for a wind turbine and with a cross
section of one coupling element mounted on the hub,
fig. 7 is a perspective view of part of equipment according to the invention to be mounted
on a hub of a wind turbine,
fig. 8 is one plane view of the part of equipment according to the invention to be mounted
on a hub of a wind turbine,
fig. 9 is another plane view of the part of equipment according to the invention to be
mounted on a hub of a wind turbine, and
fig. 10 is a third plane view of the part of equipment according to the invention to be
mounted on a hub of a wind turbine.
DETAILED DESCRIPTION OF THE INVENTION
Fig. 1 shows how equipment to be used, when conducting service on the wind turbine, is
placed, when the equipment is mounted on a hub 1. The hub 1 is mounted to the main
shaft 2 of the wind turbine, and the main shaft 2 extends from the nacelle 3 of the wind
turbine. The hub 1 is provided with an outer cap called the spinner 4, which, for the sake
of clarity, in the figure is partly cut away in order to show the mounting of the equipment
on the hub.
The equipment comprises different main parts. Primarily, a first connecting piece 5 and a
seeond connecting piece 6 is secured to the surface 7 of the hub 1. The remaining parts of
the equipment are secured to the connecting pieces so that all of the equipment via the
two coupling elements is secured to the hub. The remaining parts of the equipment
comprise a crane 8, a gangway 9 with guard rails 10, a ladder 11 leading from the nacelle
3 to the gangway 9 and a curb 12 mounted foremost on the hub 1 end being suspended
from the crane 8. The crane 8 is secured to the first connecting piece 5, and the gangway
9 is secured to the crane 8 and to the second connecting piece 6.
In the embodiment shown, the crane 8 is hoisting a hydraulic actuator 13 up to the hub 1
for replacement or for re-installation after formerly having been hoisted down for repair.
Such hydraulic actuator 13 may weigh up to 250 kg. The entire torque from the equipment
on the first connecting piece 5 must be absorbed by the securing of the first connecting
piece 5 to the surface 7 of the hub. 1. This sets extremely high demands to the securing of
the first connecting piece 5 to the hub 1. That is why persons skilled in the art have come
to the conclusions that it is hot possible.
Fig. 2 is a perspective view of the first connecting piece 5 and the second connecting piece
6, when secured to the surface 7 of the hub 1. The first connecting piece 5 consists of a


substantially cylindrical element, and the second connecting piece 6 consists of a plate-like
element. In the embodiments shown, both the first connecting piece 5 and the second
connecting piece 6 are secured to the surface 7 of the hub 1 in already existing and
available mounting holes (not shown). The already existing and available holes are holes,
which formerly have been used during erection and assembly of the wind turbine, when
hoisting, by means of a mobile crane or raft-mounted crane, the hub from the ground to
the main shaft and maintaining the hub in place during bolting of the hub to the main
shaft. Thus, the holes for securing the first connecting piece and the second connecting
piece to the surface of the hub are not initially provided for that purpose.
Fig. 3 and fig. 4 are plane drawings, fig. 5 is a perspective plane view and fig. 6 is a
perspective cross sectional view, all showing the first connecting piece 5, when being
secured to the surface 7 of the hub 1. As can be seen, the surface 7 of the hub 1 is curved
in the plane of the figure. Thus, the first connecting piece 5 must be able to adapt to the
curvature of the surface 7 of the hub 1 in order to obtain a proper securing of the first
connecting piece 5 to the hub. Only by achieving a proper securing will the first connecting
piece 5 be able to hold the crane 8, even when the crane is lifting heavy appliances to the
hub such as hydraulic actuators to be mounted inside the hub.
The first connecting piece 5 is provided with means for passing five bolts 14 through the
connecting piece 5 from a top of the connecting piece 5 and to the threaded holes 15
already provided and available in the surface 7 of the hub 1. The bolts 14 extend through
guiding liners 16 inside the first connecting piece 5, the guiding liners 16 extending from
an upper internal disc-like structure 17 to a lower disc-like structure 18 and through the
lower disc-like structure 18 into a bottom cavity 19 of the first connecting piece 5. The
bottom cavity 19 is delimited by the lower disc-like structure 18 and by a lower flange 20
of the first connecting piece 5.
The bottom cavity 19 is intended for taking up of a cement-like substance (not shown)
creating a physical connection between an under-side 21 of the lower disc-like structure 18
and the surface 7 of the hub 1. The cement-like substance is intended for creating a
completely homogeneous connection between the surface 7 of the hub 1 and the first
connecting piece 5. Because the surface 7 of the hub 1 is not worked more than absolutely
necessary, when being manufactured, the surface 7 of the hub 1 is somewhat rough. If
perhaps the first connecting piece had a concave surface being made of metal like the
connecting piece itself and being congruent with the convex surface of the hub, the
abutment between the concave surface of the first connecting piece and the convex
surface of the hub would not be homogeneous, because of the rough surface of the hub.


However, introducing a cement-like substance into the cavity 19 made in the very bottom
of the first connecting piece 5, the cement-like substance will fill out any unevenness of
the rough surface 7 of the hub 1 and will also fill out the entire cavity 19 in the bottom of
the first connecting piece 5. Thus, a complete congruent and homogenous abutment will
be established between the underside 21 of the lower disc-like structure 18 and the
surface 7 of the hub 1. This complete congruent and homogenous abutment is necessary
in order for the first connecting piece to be able to carry the loads lowered or hoisted by
the crane, without the risk of the crane tilting and breaking loose from the surface of the
hub together with the first connecting piece. Preferred cement-like substances are
substances from the Danish company Densit A/S, said substances being very hard and
durable, although being workable when yet not cured.
Fitting of the first connecting piece 5 to the surface 7 of the hub 1 takes place by initially
inserting a threaded end-of the bolts 14 into the already available holes 15 in the surface 7
of the hub 1. The holes 15, as mentioned, are previously being made, when manufacturing
the hub, and is, until now, only intended for hoisting, by means of a large crane, the hub
from the ground to the mounting flange of the main shaft.
Subsequently to the insertion of the bolts 14 into the already available holes 15, the bolts
14 are fastened or nuts 22, as shown, at threaded other ends of the bolts 14 are fitted and
fastened. Because the number of bolts 14 are limited to the number of already available
holes 15, and because the holes 15, and thus the bolts 14, are situated quite close, the
bolts 14 or the nuts 22 must befastened quite much in order for the crane 8 to be able to
hoist the sometimes heavy appliances to the hub 1. Eventually, the bolts 14 or nuts 22 are
fastened up to 50% of the yield point of the bolts. Depending on the size of the already
available holes 15, the bolts 14 may have different sizes, however a typical size being M30
bolts, i.e. having a diameter of 30 mm.
Alternatively to providing a congruent and homogeneous abutment between the often
rather rough surface of the hub and the first connecting piece, the surface of the hub, onto
which the first connecting piece is to be mounted, may be worked so that a smoother
surface is established. This may establish the possibility of a bottom surface of the first
connecting piece being a machined surface, being concave and being the abutment surface
towards the surface of the hub in stead of a cement-like substance.
A flange 23 on the outer circumference of the first connecting piece 5 is provided with
threaded holes 24 for securing by bolts (not shown) of the crane 8 to the first connecting
piece 5. Therefore, a corresponding flange is provided on the crane (see fig. 7).


The bottom flange 20 assisting in the establishment of the cavity 19 for the cement-like
substance is provided with small bolts 25 extending through threaded holes (not shown) in
the bottom flange 20. Because the bottom flange 20 is inclined an angle a, as shown, the
bolts 25 are also inclined as shown, i.e. with the end of the blots extending into the cavity
19 and directed towards the bottom of the first connecting piece and towards the surface 7
of the hub 1.
The bolts 25 are not intended for further securing of the first connecting piece 5 to the
surface 7 of the hub 1. The bolts 25 are intended for being tightened and thus being urged
into the cavity 19. Because the end of the bolts extending into the cavity are inclined
towards the bottom of the first connecting piece and towards the surface 7 of the hub 1,
then, when tightening the bolts, the end of the bolts at one time during the tightening will
meet the surface 7 of the hub 1. Further tightening of the bolts 25 will cause the first
connecting piece 5 to raise itself from the surface 7 of the hub 1 and free the first
connecting piece 5 from the hub 1, if the bolts 14 initially are loosened. This technique is
used, when the first connecting piece 5 has been used for supporting the crane 8 and no.
longer is to be used, but has to be freed from the surface 7 of the hub 1 so that the wind
turbine can come into operation again.
Fig. 7 is a perspective view and fig. 8, fig. 9 and fig. 10 are plane views of a crane 8
according to the invention. The crane 8 has a mast 30 and a jib 31, the jib 31 being
connected to the mast 30 by a hinged connection 32. The mast 30 has a flange 33
intended for being secured to the flange 23 of the first connecting piece 5. A plurality of
bolts 34 is provided for securing the crane 8 to the first connecting piece 5.
Above the flange 33 along the mast 30, four studs 35 extend outwards from the mast 30
on opposite sides of the mast 30. The studs 35 are intended for carrying the front-most
part of the gangway (see fig. 1). Preferably, the studs 35 are made of a material lighter
than steel such as an aluminium alloy in order to reduce the overall weight of the crane 8.
A preferred alloy is Alumec from Uddeholm Tooling having a module of elasticity being
about 1/3 that of steel, but has rigidity being about the same as for steel. The studs 35 are
mounted in bushings 36 provided in the mast 30. Thus, in the embodiment shown, the
studs 35 consist of four studs in total extending trough the bushings 36 in the mast 30 and
projecting on each side of the mast 30.
An. upper link 37 and a lower link 38 are provided between the mast 30 and the hinged
connection 32. Thus, the hinged connection 32 is provided at an outmost end of the links
37,38. The links 37.38 are made from a material being: very light in order to reduce the
overall weight of the crane 8. The links 37,38 have a shape, resulting in the links 37.38


converging from a greater dimension at the mast 30 of the crane 8 to a smaller dimension
at the hinged connection 32. In a preferred embodiment, the links are also made of a
material being lighter than steel such as an aluminium alloy, preferably Aiumec from
Uddeholm Tooling having, as mentioned, a module of elasticity being about 1/3 that of
steel, but having rigidity being equal to that of steel. Thus, the strength of the links is not
compromised.
. The jib 31 is made of a material being rigid enough to carry the load to be hoisted, but still
being as light-weighted as possible in order to reduce the overall weight of the crane 8 and
especially the weight contributing much to the torque applied to the first connecting piece.
In a preferred embodiment the jib 31 is made of Alumec from Uddeholm Tooling. Between
the lower link 38 and the jib 31 a hydraulic actuator 39 is provided. The hydraulic actuator
39 is intended for swivelling the jib 31 around the hinged connection 32 in relation to the
links 37,38 and in relation to the mast 30 and the hub 1, onto which the crane 8 is
mounted.
From an upper part of the hinged connection 32 and obliquely downward to an out-most
end, although not outer-most end, of the jib 31, a brace 40 is inserted. The jib 31 is a so-
called IPE-profile, and the lowering and hoisting means consists of a trolley 41 with a wire
42. The trolley 41 preferably has a set of two or more wheels 43 on each side of the jib 31.
Thereby, the trolley 41 has the advantage of distributing the load along the length of the
jib 31. Thereby, the jib 31 may be made using as little material as possible in relation to
the weight to be lowered and hoisted by the wire 42 and thus in consideration of the total
weight of the jib 31 and the crane 8. In the embodiment shown, the outer-most point of
the jib is situated in a distance from the crane mast centre of about 2.5m.

WE CLAIM:
1. Equipment for servicing a wind turbine after a hub (1) of the wind
turbine has been mounted, said equipment comprising a crane (8) for
lowering and hoisting wind turbine appliances from and to the hub
(1), characterized in that connecting means (5,6) are provided for
primarily securing the equipment including the crane (8) to a curved
surface (7) of the hub, and receiving the load of the crane thereon,
the connecting means having a lower surface adapted to conform to
the hub curved surface (7).
2. Equipment as claimed in claim 1, said equipment being provided
with fastening means, preferably bolts (14), for securing the
equipment to already available holes (15), said holes formerly used for
hoisting the hub (1) to the main shaft of the wind turbine.
3. Equipment as claimed in claim 2, wherein the connecting means
comprises a first connecting piece (5) intended for being secured to a
generally upwardly facing region of the hub curved surface (7) in a
first set of already available holes.
4. Equipment as claimed in claim 2 or 3, wherein the equipment is
provided with a second connecting piece (6) intended for being
secured to the curved hub surface (7) in a second set of already
available holes.
5. Equipment as claimed in claim 3 , wherein the first connecting
piece (5) is intended primarily for securing a crane, constituting part
of the equipment, to the hub.


6. Equipment as claimed in claim 4 wherein the second connecting
piece (6) is intended primarily for securing a gangway (9), constituting
part of the equipment, to the hub.
7. Equipment as claimed in claim 3, wherein said first connecting
piece for connecting the hub with the remainder of the equipment is
provided with primary holes for inserting bolts (14) to be secured to
the existing holes in the hub and thereby securing the connecting
piece to the hub, and said connecting piece also being provided with
secondary holes (24) for inserting bolts for securing the remainder of
the equipment to the connecting piece.
8. Equipment as claimed in claim 7, wherein a cavity (19) is formed in
a bottom of the first connecting piece (5) , said cavity (19) being
intended for containing a cement-like substance when the connecting
piece is secured to the hub.
9. Equipment as claimed in claim 8, wherein the cavity is delimited
by a collar (20) extending circumferentially along the bottom of the
connecting piece, and said collar limiting any flow from the cavity of
the cement-like substance.

10. Equipment as claimed in any one of claims 7 to 9, wherein the
connecting piece (5), preferably the collar (20) of the connecting piece,
is provided with means (25) for releasing the adherence by the
cement-like structure of the connecting piece to the hub.
11. Equipment as claimed in claim 8 or 9 , wherein the cavity (19) is
delimited by a lower disc-like member (18) extending inside the


connecting piece, and said lower disc-like member limiting any flow
from the cavity of the cement-like substance.
12. Equipment as claimed in claim 11, wherein the connecting piece
(5) comprises a flange (23) extending circumferentially along the
connecting piece, said flange being provided with means (24) for
securing the remainder of the equipment to the connecting piece.
13. Equipment as claimed in claim 11 or 12, wherein the connecting
piece is provided with an upper disc-like member (17) and guiding
liners (16) for bolts extend between the upper disc-like member (17)
and the lower disc-like member (18).
14. Equipment as claimed in any of the claim 13, wherein the guiding
liners (16) are positioned relative to each other in the connecting
piece corresponding to a positioning of already available holes in the
hub of the wind turbine.
15. Equipment as claimed in any preceding claim, wherein said crane
is provided with primary holes for inserting bolts for securing the
crane to the first connecting piece (5) and thus to the hub.
16. Equipment as claimed in any preceding claim , wherein the crane
(8) is provided with a jib (31) connected to a mast (30) of the crane,
said jib (31) being swivelable around a substantially vertical hinged
connection (32) and said jib (31) extending outwards in relation to the
mast and forwards in relation to a direction being a forwards
direction of the wind turbine when the crane is secured to the hub.


17. Equipment as claimed in claim 16, wherein links (37,38) are
provided between the mast (30) and the hinged connection, said links
extending outwards in relation to the mast and forwards in relation to
a direction being a forwards direction of the wind turbine when the
crane is secured to the hub.
18. Equipment as claimed in claim 17, wherein the links (37,38) have
a greater dimension at an end where the links are attached to the
mast (30) and have a smaller dimension at an end where the jib by
means of the hinged connection (32) is attached to the links.
19. Equipment as claimed in claim 17 or 18, wherein the links
(37,38) are made of a material less dense than steel.
20. Equipment as claimed in any one of claims 16 to 19 , wherein the
jib (31) has an I-shaped or inverted T-shaped cross section, and the
wheels of a trolley are intended for being supported on the
transversal parts of the profile.
21. A method of conducting service on a wind turbine utilizing the
equipment as claimed in any one of claims 1 to 20, the method
involving the mounting of the equipment onto the curved surface (7)
of the wind turbine hub (1) by securing the connecting means (5) to
the hub curved surface, and employing the crane to lower and hoist
wind turbine appliances from and to the hub.
22. A method as claimed in claim 21 wherein the connecting means
(5) is secured to holes on the curved hub surface (7) previously
employed for hoisting the hub when erecting the turbine.


23. A method as claimed in claim 21 or 22 wherein the equipment
extends forwardly over the hub (1), whereby the appliances are
hoisted over a front of the hub.


Equipment for servicing a wind turbine after a hub (1) of the
wind turbine has been mounted, said equipment comprising a crane
(8) for lowering and hoisting wind turbine appliances from and to the
hub (1), characterized in that connecting means (5, 6) are provided
for primarily securing the equipment including the crane (8) to a
curved surface (7) of the hub, and receiving the load of the crane
thereon, the connecting means having a lower surface adapted to
conform to the hub curved surface (7).

Documents:

00781-kolnp-2006-abstract.pdf

00781-kolnp-2006-claims.pdf

00781-kolnp-2006-description complete.pdf

00781-kolnp-2006-drawings.pdf

00781-kolnp-2006-form 1.pdf

00781-kolnp-2006-form 3.pdf

00781-kolnp-2006-form 5.pdf

00781-kolnp-2006-international exm report.pdf

00781-kolnp-2006-international publication.pdf

00781-kolnp-2006-international search report.pdf

781-KOLNP-2006- L.P CORRECTION.PDF

781-KOLNP-2006-(06-02-2012)-CORRESPONDENCE.pdf

781-KOLNP-2006-(06-02-2012)-FORM-1.pdf

781-KOLNP-2006-(06-02-2012)-FORM-13.pdf

781-KOLNP-2006-(06-02-2012)-PA-CERTIFIED COPIES.pdf

781-KOLNP-2006-(13-09-2011)-CORRESPONDENCE.pdf

781-KOLNP-2006-(13-09-2011)-FORM 1.pdf

781-KOLNP-2006-(13-09-2011)-FORM 2.pdf

781-KOLNP-2006-(13-09-2011)-FORM 3.pdf

781-KOLNP-2006-(13-09-2011)-FORM 5.pdf

781-KOLNP-2006-(13-09-2011)-OTHERS.pdf

781-KOLNP-2006-(30-04-2012)-CORRESPONDENCE.pdf

781-KOLNP-2006-(30-04-2012)-FORM-1.pdf

781-kolnp-2006-abstract.pdf

781-KOLNP-2006-ASSIGNMENT.pdf

781-KOLNP-2006-CERTIFIED COPIES(OTHER COUNTRIES).pdf

781-kolnp-2006-claims.pdf

781-KOLNP-2006-CORRESPONDENCE 1.1.pdf

781-KOLNP-2006-CORRESPONDENCE 1.3.pdf

781-KOLNP-2006-CORRESPONDENCE.pdf

781-kolnp-2006-description (complete).pdf

781-kolnp-2006-drawings.pdf

781-kolnp-2006-form 1-1.1.pdf

781-KOLNP-2006-FORM 1-1.2.pdf

781-KOLNP-2006-FORM 1.pdf

781-KOLNP-2006-FORM 13.pdf

781-KOLNP-2006-FORM 2-1.1.pdf

781-KOLNP-2006-FORM 2.pdf

781-KOLNP-2006-FORM 3-1.1.pdf

781-kolnp-2006-form 3-1.2.pdf

781-KOLNP-2006-FORM 3-1.3.pdf

781-KOLNP-2006-FORM 3.pdf

781-KOLNP-2006-FORM 5 1.1.pdf

781-KOLNP-2006-FORM 5-1.2.pdf

781-KOLNP-2006-FORM 5.pdf

781-KOLNP-2006-FORM 6.pdf

781-kolnp-2006-others.pdf

781-KOLNP-2006-PA 1.1.pdf

781-KOLNP-2006-PA.pdf

781-KOLNP-2006-PCT IPER.pdf

781-KOLNP-2006-REPLY TO EXAMINATION REPORT.pdf

abstract-00781-kolnp-2006.jpg


Patent Number 250397
Indian Patent Application Number 781/KOLNP/2006
PG Journal Number 01/2012
Publication Date 06-Jan-2012
Grant Date 02-Jan-2012
Date of Filing 31-Mar-2006
Name of Patentee VESTAS WIND SYSTEMS A/S
Applicant Address A DANISH COMPANY ALSVEJ 21, DK-8940 RANDERS SV DENMARK
Inventors:
# Inventor's Name Inventor's Address
1 PEDERSEN, BJARNE KJÆ RSLUND 21, 2. TV. DK-8260 VIBY J
PCT International Classification Number F03D 1/00
PCT International Application Number PCT/DK2004/00635
PCT International Filing date 2004-09-18
PCT Conventions:
# PCT Application Number Date of Convention Priority Country
1 PA 2003 01401 2003-09-26 Denmark