Title of Invention

TEMPORARY SOIL SHEATHING APPARATUS

Abstract A temporary soil sheathing apparatus supports a set of intermediate bracing beams in a triangular supporting structure during pit excavation work for constructing an underground structure, so that it can satisfactorily support soil pressure. Thus, it is possible to prevent space from being reduced by a complicated supporting structure, reduce construction costs through reduced use of materials, and increase work space to improve productivity. The temporary soil sheathing apparatus simplifies a corner connecting structure, and reinforces ability to withstand the soil pressure transmitted from the bracing beams and wales. Thereby, it is possible to prevent space from being reduced by a complicated supporting structure, reduce construction costs through reduced use of materials, and increase work space to thus improve productivity.
Full Text Technical Field
The present invention relates, in general, to a temporary soil sheathing apparatus,
and more particularly, to a temporary soil sheathing apparatus capable of increasing
ability to withstand soil pressure through structural simplification during pit excavation
work for constructing an underground structure.
Background Art
As is generally known in the art, in subway construction or in pit excavation work
for forming the basement of a building, holes are drilled to a predetermined depth in a
designated area, and then vertical piles are sunk into the holes. After the vertical piles
are sunk, the ground is partially excavated, and then H-beams and lining boards are
installed. After installing the lining boards, the remaining ground is excavated, and
bracing beams are repeatedly installed, accompanied with excavation. Therefore, in
order to design this temporary structure, the soil pressure and the load acting on each
bracing beam must be repeatedly calculated, once for each excavation step, and the
bracing beams are installed so as to be able to withstand the maximum soil pressure
and load determined thus.
This design and construction requires many bracing beams. In most cases, the
bracing beams are densely arranged at intervals between 2 m and 3 m. The dense
bracing beams serve as main obstacles that impede the transport of construction
materials, the entry and operation of heavy equipment, etc. in the excavated pit, and
interfere considerably with form work or reinforcement work when the main structure
is subsequently formed. Further, the dense bracing beams inevitably require that a
plurality of holes be formed in the main structure, so that they cause a serious problem
with respect to the waterproofing of the finished underground structure.
The vertical piles are set up according to various methods, such as a method of
using H-beams of steel, a method of using concrete piles in which holes are drilled and
filled with concrete, a method of using H-beams together with concrete piles, and a
method of using sheet piles. These methods make little difference with respect to the
basic principle of drilling holes into the ground, forming piles into a wall, and
supporting the load of the ground.
Further, there are other methods: a method of using preflex beams as the vertical
piles, and a method of attaching sheet piles to H-piles to increase rigidity.
Meanwhile, among the temporary methods for constructing the underground
structure, there is a method of supporting steel piles using earth anchors that does not

require the above-described bracing beams.
This method involves drilling a hole at an incline into the ground at the rear of the
pile, inserting a steel wire or rod into the hole, anchoring an end of the inserted steel
wire or rod using a mechanical method or a chemical method, such as epoxy grouting
or cement grouting, and tensioning the anchored steel wire or rod to fix the steel piles.
This temporary method has an advantage in that the problem in that it is difficult to
conduct work is mitigated because the constructed structure secures sufficient internal
space.
However, this temporary is widely criticized by the public when implemented in a
developed urban area because the surrounding private land is encroached upon in most
cases, and furthermore, the method costs a great deal.
A method of removing bracing beams crossing an excavated pit from a temporary
structure using a truss is disclosed in Korean Utility Model Registration No.
20-258949. This method is expected to be able to be applied in the case in which the
ground is excavated to a relatively low depth, wherein H-beams are doubly formed
near the surface of land in a lattice shape and are reinforced by vertical beams and
raker beams. Thereby, the two-tier truss near the surface of land is made able to
withstand the soil pressure.
This method was devised to overcome difficulty in excavation and installation of
the main structure due to the bracing beams of the temporary structure, and is regarded
as a convenient method in the situation where a wide structure is to be formed in a
lower portion of the excavated ground and a narrow structure is to be formed in an
upper portion of the excavated ground.
Typically, the bracing beams are primarily used in pit excavation work. During
such work, when viewed from the top, the moment is maximized at the central portion
in the rectangular area by means of the soil pressure, so that the central portion must
have greater bearing capacity than other portions.
Therefore, the central portion requires a lot of central bracing beams. This becomes
a factor that increases construction costs and makes the structure complicated.
Thereby, the work space is narrowed, thus reducing productivity.
Disclosure of Invention
Technical Problem
Accordingly, the present invention has been made in an effort to solve the problems
occurring in the related art, and an object of the present invention is to provide a
temporary soil sheathing apparatus, in which a set of intermediate bracing beams
having a preloading jack in the middle thereof and a triangular supporting structure at
opposite ends thereof is installed at an intermediate excavated portion during pit

excavation work for constructing an underground structure, thereby increasing the
capacity to bear soil pressure through structural simplification.
Another object of the present invention is to provide a temporary soil sheathing
apparatus, in which a corner connecting structure is applied to each corner of an
excavated portion during pit excavation work for constructing an underground
structure, thereby increasing ability to withstand soil pressure through structural sim-
plification.
Another object of the present invention is to provide a temporary soil sheathing
apparatus, in which bracing beams are interconnected at each corner of an excavated
portion during pit excavation work for constructing an underground structure, thereby
forming the bracing beams, to which soil pressure is transmitted, into a truss structure
such that the bracing beams behave like one member.
Technical Solution
In order to achieve the above objects, according to one aspect of the present
invention, there is provided a temporary soil sheathing apparatus, which includes: a set
of intermediate bracing beams are is installed across an intermediate portion excavated
in a rectangular area during underground pit excavation work, and wales that are
integrally connected with opposite ends of the intermediate bracing beam set. Here, the
intermediate bracing beam set is provided with a preloading jack at the middle thereof,
and is connected with raker beams via first and second connectors on left and right
sides of each end thereof, such that the opposite ends thereof form a triangular
supporting structure.
According to another aspect of the present invention, there is provided a temporary
soil sheathing apparatus, which includes a braced wall that is installed parallel to an
excavated portion during underground pit excavation work, a set of bracing beams that
are coupled to the braced wall at each corner in the pit excavation work and support
soil pressure, and a corner connector having a cross beam that is coupled to each wale,
a compression beam that is obliquely connected to one end of the cross beam and is
integrally connected to one end of the bracing beam set, and a raker beam that connects
one end of the compression beam and another end of the cross beam.
According to yet another aspect of the present invention, there is provided a
temporary soil sheathing apparatus, which includes bracing beams that are disposed in
rows at predetermined intervals so as to support each corner during underground pit
excavation work, and at least one connecting plate that is integrally coupled to any one
of upper and lower surfaces of each bracing beam by a coupling means so as to in-
terconnect the bracing beams.
Advantageous Effects

According to a first embodiment of the present invention, the temporary soil
sheathing apparatus is adapted to simplify the connecting structure of the intermediate
bracing beam set and reinforce the ability to withstand the soil pressure transmitted
from the braced wall and the wales during rectangular pit excavation work for con-
structing an underground structure. Thus, the temporary soil sheathing apparatus has a
triangular supporting structure that supports the intermediate bracing beam set in the
pit excavation work for constructing an underground structure, so that it can satis-
factorily support soil pressure. Thus, it is possible to prevent space from being reduced
by a complicated supporting structure, reduce construction costs through reduced use
of materials, and increase work space to thus improve productivity.
Further, the opposite ends of the intermediate bracing beam set are supported in a
triangular supporting structure. Hence, the braced wall to which the soil pressure is
actually transmitted can be supported by a wider supporting area compared to existing
structures for connecting the intermediate bracing beams, so that it is possible to simul-
taneously apply an amount of compressive force corresponding to the soil pressure and
increase bearing capacity.
According to a second embodiment of the present invention, the temporary soil
sheathing apparatus is adapted to simplify the connecting structure in each corner and
reinforce the ability to withstand the soil pressure transmitted from the braced wall and
the wales during pit excavation work for constructing an underground structure.
Thereby, the temporary soil sheathing apparatus can satisfactorily support the soil
pressure transmitted to each corner using a simple corner connecting structure during
pit excavation work for constructing an underground structure, so that it is possible to
prevent space from being reduced by a complicated supporting structure, reduce con-
struction costs through reduced use of materials, and increase work space to thus
improve productivity.
According to a third embodiment of the present invention, the temporary soil
sheathing apparatus is adapted to interconnect the bracing beams disposed in rows at
each corner during pit excavation work for constructing an underground structure. The
temporary soil sheathing apparatus integrates the rows of bracing beams at each corner
in a truss structure, so that it can uniformly transmit a horizontal load, and thus obtain
sufficient durability against a flexural load.
Brief Description of the Drawings
FIG. 1 is a schematic top plan view illustrating a temporary soil sheathing apparatus
according to a first embodiment of the present invention;
FIG. 2 is a perspective view illustrating an important part in a temporary soil
sheathing apparatus according to a first embodiment of the present invention;

FIG. 3 is a top plan view illustrating a first connector, which is an important part, in
a temporary soil sheathing apparatus according to a first embodiment of the present
invention;
FIG. 4 is a top plan view illustrating a connecting structure of a second connector,
which is an important part, in a temporary soil sheathing apparatus according to a first
embodiment of the present invention;
FIG. 5 is a schematic top plan view illustrating a temporary soil sheathing apparatus
according to a second embodiment of the present invention;
FIG. 6 is an enlarged perspective view illustrating part A of FIG. 5;
FIG. 7 is a sectional view illustrating an important part of FIG. 6;
FIG. 8 is a partial top plan view illustrating a modification of the corner connecting
structure of FIG. 5;
FIG. 9 is a top plan view illustrating a temporary soil sheathing apparatus according
to a third embodiment of the present invention;
FIG. 10 is an enlarged perspective view illustrating part B of FIG. 9;
FIG. 11 is a top plan view illustrating an important part of FIG. 9;
FIG. 12 is a front view illustrating an important part of FIG. 9; and
FIG. 13 is a front view illustrating a modification of FIG. 12.
Best Mode for Carrying Out the Invention
Reference will now be made in greater detail to exemplary embodiments of the
invention with reference to the accompanying drawings.
[Embodiment 1]
Referring to FIGS. 1 through 4, a temporary soil sheathing apparatus according to a
first embodiment of the present invention includes wales 20 that are integrally coupled
to a braced wall (not shown), installed parallel to a vertically excavated portion in a
rectangular area during pit excavation work, and that support soil pressure, a set of in-
termediate bracing beams 100 that traverse long sides of the braced wall and that
support the soil pressure transmitted from the braced wall, raker beams 200 that
obliquely support the intermediate bracing beam set 100 and the corresponding wale
20 at opposite ends thereof so as to be connected with the intermediate bracing beam
set 100 and the corresponding wale 20 in a triangular structure.
More specifically, the intermediate bracing beam set 100 comprises a plurality
thereof, and has a structure in which each intermediate bracing beam is connected so as
to be integrally coupled to the wales 20 at opposite ends thereof, and is provided with a
preloading jack 150 at the middle thereof, thereby having varying ability to withstand
the soil pressure.
Each wale 20 may employ a single-layer wale or a multi-layer wale depending on

the footprint of the excavated ground, and is preferably pre-stressed so as to match (the
moment of) the soil pressure.
Each raker beam 200 is installed obliquely with respect to the intermediate bracing
beam 100 and the corresponding wale 20, thereby forming a triangular structure. The
raker beam 200 is integrally connected to the intermediate bracing beam set 100 and
the corresponding wale 20, respectively, through first and second connectors 310 and
320 at opposite ends thereof. The first and second connectors 310 and 320 have an ap-
proximately triangular shape so that they can support the opposite ends of each raker
beam 200.
The first connector 310 is interposed between the intermediate bracing beam set
100 and the raker beam 200, and includes a vertical beam 312 that is connected to the
intermediate bracing beam set 100, and first and second supporting beams 314 and 316
that are obliquely connected to opposite ends of one side of the vertical beam 312 so as
to have a triangular shape.
Further, the second connector 320 is interposed between the raker beam 200 and the
corresponding wale 20, and includes a cross beam 322 that is parallel to and in surface
contact with the wale 20, and first and second connecting beams 324 and 326 that are
obliquely connected to opposite ends of one side of the cross beam 322 and integrally
coupled to the other end of the raker beam 200 so as to have a triangular shape.
The cross beam 322 of the second connector 320 is bolted on one side of the wale
20, and the first and second connecting beams 324 and 326 serve to distribute and
support the load transmitted from the raker beam 200.
Preferably, the beams of the first and second connectors 310 and 320 each employ a
typical H-beam having a web and flanges. At least one first stiffener 310a is welded to
the web of the H-beam for the first connector 310, and at least one second stiffener
320a is welded to the web of the H-beam for the second connector 320.
Each of the first and second stiffeners 310a and 320a is preferably provided so as to
support compressive force at a portion where another member is coupled or force is
transmitted.
Further, the cross beam 322 and the vertical beam 312 have end plates welded at
opposite ends thereof in order to be connected with the corresponding wale 20 and the
intermediate bracing beam set 100, respectively.
Also, the first and second connectors 310 and 320 have first and second reinforcing
plates 310b and 320b interposed between the vertical beam 312 and the first supporting
beam 314 and between the cross beam 322 and the first connecting beam 324, re-
spectively. Thus, the first and second connectors 310 and 320 are in surface contact
with two sides of each of the first and second reinforcing plates 310b and 320b, so that
they can increase the ability to withstand compressive force.

The wale 20 is preferably provided with a shear key 322a at the position where the
compressive force is transmitted. The shear key 322a is connected by high-tensile
bolts, and is in contact with one flange of the cross beam 322.
Because the compressive force transmitted to the wale 20 and the force transmitted
from the raker beam 200 act in opposite directions, the shear key 322a serves to use the
opposing forces to offset each other.
The operation of the temporary soil sheathing apparatus, having this construction,
according to a first embodiment of the present invention, will be described below.
The temporary soil sheathing apparatus according to a first embodiment of the
present invention is adapted to support soil pressure on an intermediate portion which
is transmitted through the braced wall by installing the raker beams 200 for connection
with the wales 20 so as to have a triangular supporting structure at opposite ends of the
intermediate bracing beam set 100.
At this time, the preloading jack 150 installed at the intermediate portion, preferably
at the center, of the intermediate bracing beam set 100 transmits a load in opposite
directions. Thereby, the opposite ends of the intermediate bracing beam set 100 apply
pressure to the opposite wales 20, and thus transmit compressive bearing force cor-
responding to the soil pressure to the opposite wales 20.
Further, the compressive force transmitted from the opposite wales 20 is distributed
and supported through the raker beam 200 installed on the opposite ends of the in-
termediate bracing beam set 100 to form a triangular shape, so that stable bearing
capacity can be obtained.
The pressure transmitted through each wale 20 is transmitted to the end plates of
each cross beam 322, which is in surface contact with a stopper of a corresponding
wale 20. In the case in which each cross beam 322 is in contact with the shear key
322a, the compressive force transmitted from each wale 20 acts to oppose the pressure
transmitted to the cross beam 322 through the intermediate bracing beam set 100. As a
result, these forces can be offset and counteracted by each other, and simultaneously
the bearing capacity can be provided by high-tensile bolts.
Further, the raker beams 200 are connected to the intermediate bracing beam set
100 and the opposite wales 20 to form a triangular supporting structure, so that the
compressive forces from the opposite wales can be distributed and supported in a more
stable way.
Further, the first and second stiffeners 310a and 320a are welded to the webs of the
first and second connectors employing H-beams, respectively, so that they can increase
rigidity and ability to withstand compressive force. Further, the first and second
connectors 310 and 320 are provided with the first and second reinforcing plates 310b
and 320b, respectively, so that they can make up for the ability to withstand the

compressive force transmitted from the raker beams 200.
[Embodiment 2]
The temporary soil sheathing apparatus according to a second embodiment of the
present invention further includes a corner connecting structure employing the
triangular supporting structure employed in the temporary soil sheathing apparatus
according to the first embodiment of the present invention. In this case, the temporary
soil sheathing apparatus can increase the efficiency of use of space and the ability to
withstand soil pressure through structural simplification.
The temporary soil sheathing apparatus according to a second embodiment of the
present invention further includes a corner connecting structure employing the above-
described triangular supporting structure. Referring to FIGS. 5 through 8, the
temporary soil sheathing apparatus according to a second embodiment of the present
invention includes a braced wall 510 that is installed parallel to a vertically excavated
portion during pit excavation work, wales 520 and bracing beam sets 550 that are
integrally coupled to the braced wall 510 and support soil pressure, and corner
connectors 600 that are provided at corners formed by the braced wall 510 and support
the soil pressure transmitted from the braced wall 510.
More specifically, each bracing beam set 550 may be replaced by a strut, and each
wale 520 can be pre-stressed so as to match the moment of the soil pressure. Further,
each wale 520 may employ a single-layer wale or a multi-layer wale in consideration
of the footprint and the depth of the excavated ground.
Each corner connector 600 includes a cross beam 610, a compression beam 620,
and a raker beam 630, all of which form a stable structure when pressure is transmitted
thereto, i.e. a triangular structure. Here, the cross beam 610 is integrally coupled with
the corresponding wale 520. The compression beam 620 is connected to one end of the
cross beam 610 and one end of each bracing beam set 550. The raker beam 630
connects the cross beam 610 and the compression beam 620.
The cross beam 610 is fixed to one side of the corresponding wale 520 by means of
bolts. The compression beam 620 is connected with each bracing beam set 550 on one
side thereof, and transmits the load of the soil pressure, which is transmitted from each
bracing beam set 550, to other members. The raker beam 630 serves to distribute and
support the load transmitted from the compression beam 620.
Each of the cross beam 610, the compression beam 620, and the raker beam 630
preferably employs a well-known H-beam, to the web of which at least one stiffener
650 is welded.
The stiffener 650 is preferably provided to portions where the members are coupled
or where the force is transmitted so as to support compressive force.
Further, the cross beam 610 has end plates 614 welded to opposite ends thereof in

order to be connected with the corresponding wale 520.
Also, a reinforcing plate 810 is interposed between the cross beam 610 and the
compression beam 620. The reinforcing plate 810 is in surface contact with the cross
beam 610 and the compression beam 620 on two sides thereof, so that it can increase
the ability to withstand compressive force.
The reference number "602", which has not yet been described, refers to a drain
hole for preventing rainwater from collecting in each beam.
As in FIG. 4, each wale 520 is preferably provided with a shear key 615 at a
position where the compressive force is transmitted. The shear key 615 is connected by
high-tensile bolts, and is in contact with the other side of the cross beam 610.
Because the compressive force transmitted to the wale 520 and the force transmitted
from the compression beam 620 act in opposite directions, the shear key 615 serves to
use the opposing forces to offset each other.
Although not illustrated, a preloading jack having a cylinder is provided at an in-
termediate portion of each bracing beam set 550. Preferably, each bracing beam set
550 is provided with corresponding corner connectors 600 having a triangular structure
at opposite ends thereof, thereby transmitting compressive force corresponding to the
soil pressure from the preloading jack to the compression beams 620 of the cor-
responding corner connectors 600.
The operation of the temporary soil sheathing apparatus, having this construction,
according to a second embodiment of the present invention will be described below.
The temporary soil sheathing apparatus according to a second embodiment of the
present invention is adapted to support soil pressure, transmitted through the braced
wall 510, through the corner connectors 600, installed between the bracing beam sets
550 and the wales 520 at the corners defined by the braced wall 510.
At this time, the soil pressure on the braced wall 510 is supported by the
compressive force transmitted from the bracing beam sets 550 and by the transverse
pressure transmitted from the wales 520 at the corners. The compression beam 620 of
each corner connector 600 distributes and transmits the pressure, which is transmitted
from each bracing beam set 550, to the cross beam 610 and the raker beam 630. As a
result, the temporary soil sheathing apparatus can have increased load carrying
capacity using a simple structure.
The pressure transmitted through each wale 520 is transmitted to the end plates of
each cross beam 610, which is in surface contact with the corresponding wale 520. In
the case in which each cross beam 610 is in contact with the shear key 615, the
compressive force transmitted from each wale 520 acts against the pressure transmitted
to each cross beam 610 through each bracing beam set 550. As a result, these forces
can be offset and counteracted by each other, and the bearing capacity can be provided

using high-tensile bolts.
Further, the stiffener 650 is welded to the web of each corner connector 600
employing the H-beam, so that it can increase rigidity and the ability to withstand the
compressive force. Further, the reinforcing plate is interposed between the cross beam
610 and the compression beam 620, so that it can increase the ability to withstand the
compressive force transmitted from each bracing beam set 550.
[Embodiment 3]
The temporary soil sheathing apparatus according to a third embodiment of the
present invention further includes a corner connecting structure which is adapted to
uniformly transmit horizontal load to thus obtain sufficient ability to withstand a
flexural load using bracing beams, disposed in rows at each corner and integrated in a
truss structure when pit excavation work for constructing an underground structure is
performed.
Referring to FIGS. 9 through 13, the temporary soil sheathing apparatus according
to a third embodiment of the present invention includes bracing beams 1100 that are
obliquely disposed in rows at each corner when pit excavation work for constructing
an underground structure is performed, and that are supported on a braced wall 1010 at
opposite ends thereof, and at least one connecting plate 1200 that interconnects upper
or lower surfaces of the neighboring bracing beams 1100 using a coupling means.
More specifically, the connecting plate 1200 has a rectangular shape, and is
provided with at least one stiffener 1210 that is oriented in a longitudinal direction in
order to resist vertical flexural deformation.
The stiffener 1210 is integrally formed at one edge of the connecting plate 1200, or
is integrated with the connecting plate 1200 through welding. The stiffener 1210 has
the shape of a strip or an L-shaped angle. Although not illustrated, the connecting plate
1200 may employ an H-beam.
FIG. 13 is a front view illustrating a modification of FIG. 12. The connecting plates
1200 are coupled to upper and lower surfaces of each bracing beam 110, respectively.
According to the circumstances of a particular site, a plurality of connecting plates
1200 is preferably used in a stacked arrangement. If necessary, the stiffener 1210 can
be omitted.
The connecting plates 1200 cause the rows of bracing beams 1100 to be disposed in
parallel in a truss structure, and function to uniformly transmit the load without leaning
to one side.
Each bracing beam 1100 is connected with wales 1020, which are integrally
coupled to the braced wall 1010, at opposite ends thereof. Alternatively, each bracing
beam 1100 is connected with the wales 1020 at opposite ends thereof by means of
separate structures.

The coupling means functions to integrate the connecting plate 1200 and the
bracing beams 1100 by means of welding or well-known fastening members using, for
instance, bolts 1310 and nuts 1320. When using the fastening members, each bracing
beam 1100 and the connecting plate 1200 are provided with a lot of through-holes
1102 and 1202 for fastening the bolts 1310, respectively. The bolts 1310 pass through
the through-holes 1102 and 1202, and then are fastened by the nuts 1320.
The reference number "1150", which has not yet been described, indicates a bearing
beam that bears the bracing beams 1100 in a transverse direction. At least one bearing
beam 1150 is integrally fastened to the lower surface of each bracing beam 1100 by
means of the bolts 1310, thereby serving to prevent the bracing beams 1100 from being
bent upwards and/or downwards by the load.
The operation of the temporary soil sheathing apparatus, having this construction,
according to a third embodiment of the present invention will be described below.
The temporary soil sheathing apparatus according to a third embodiment of the
present invention is adapted to interconnect the plurality of rows of bracing beams
1100, which are disposed in parallel at each corner when pit excavation work for con-
structing an underground structure is performed, using the connecting plates 1200
having a rectangular shape, so that the bracing beams 1100 spaced apart from each
other are connected into one structure, thereby behaving in a unified way with respect
to a load transmitted from each end thereof. Thus, the load is uniformly transmitted to
each bracing beam 1100, and the bracing beams 1100 are prevented from deviating or
flexing.
At this time, the connecting plates 1200 are in surface contact with the upper and/or
lower surface of each bracing beam 1100, and the through-holes 1102 and 1202 are
aligned in a vertical direction. Then, the bolts 1310 pass through the through-holes
1102 and 1202, and are fastened by the nuts 1320. Thereby, the assembly of the
temporary soil sheathing apparatus is completed.
When the assembly is completed, the bracing beams 1100 have a truss structure at
each corner, defined by the braced wall. Therefore, the bracing beams 1100 react to a
transmitted load in an integrated manner, and thereby have sufficient resistance to
horizontal flexural load.
Further, the stiffener 1210 protruding outwards from one surface of each connecting
plate 1200 is welded to each connecting plate 1200, so that the bracing beams 1100 can
resist upward flexure while the load of each bracing beam 1100 is transmitted.
Meanwhile, when the underground structure is sufficiently stable to prevent the
ground from collapsing, the temporary soil sheathing apparatus is disassembled and
reused. At this time, the connecting plates 1200 are separated from each bracing beam
1100 by unfastening the bolts 1310 and the nuts 1320.

The connecting plates 1200 can vary in size depending on the interval between the
rows of bracing beams 1100. Therefore, each connecting plate 1200 is not required to
have a fixed size.

We Claim:-
[1] A temporary soil sheathing apparatus, comprising:
a set of intermediate bracing beams that is installed across an intermediate
portion excavated in a rectangular area during underground pit excavation work;
and
wales that are integrally connected with opposite ends of the intermediate
bracing beam set,
wherein the intermediate bracing beam set is provided with a preloading jack at a
middle thereof, and is connected with raker beams via first and second
connectors on left and right sides of each end thereof, such that the opposite ends
thereof form a triangular supporting structure.
[2] The temporary soil sheathing apparatus as set forth in claim 1, wherein each first
connector is interposed between one side of the intermediate bracing beam set
and one end of each raker beam, and includes a vertical beam that is connected to
the intermediate bracing beam set, and first and second supporting beams that are
obliquely connected to opposite ends of one side of the vertical beam so as to
form a triangular shape.
[3] The temporary soil sheathing apparatus as set forth in claim 1, wherein each
second connector is interposed between another end of each raker beam and each
wale, and includes a cross beam that is parallel to and in surface contact with
each wale, and first and second connecting beams that are obliquely connected to
opposite ends of one side of the cross beam so as to form a triangular shape.
[4] The temporary soil sheathing apparatus as set forth in claim 3, wherein each
second connector is in surface contact with a shear key, which is provided on
each wale.
[5] The temporary soil sheathing apparatus as set forth in claim 3, wherein each of
the first and second connectors is an H-beam having a web and flanges, and at
least one stiffener is welded to the web in order to increase compressive force.
[6] The temporary soil sheathing apparatus as set forth in claim 1, further comprising
a corner connecting structure including:
a braced wall that is installed parallel to an excavated portion during un-
derground pit excavation work;
a set of bracing beams that are coupled to the braced wall at each corner during
the pit excavation work and support soil pressure; and
a corner connector, having:
a cross beam that is coupled to each wale,
a compression beam that is obliquely connected to one end of the cross beam and


is integrally connected to one end of the bracing beam set, and
a raker beam that connects one end of the compression beam and another end of
the cross beam.
[7] The temporary soil sheathing apparatus as set forth in claim 6, wherein the raker
beam and the compression beam are connected perpendicular to each other.
[8] The temporary soil sheathing apparatus as set forth in claim 6, wherein the
corner connector is an H-beam having a web and flanges, and at least one
stiffener is coupled to the web.
[9] The temporary soil sheathing apparatus as set forth in claim 6, wherein the cross
beam and the compression beam have a reinforcing plate integrally coupled
therebetween to provide reinforcement.
[10] The temporary soil sheathing apparatus as set forth in claim 6, wherein each wale
includes a shear key at a position in contact with the cross beam where
compression force thereof is transmitted.
[11] The temporary soil sheathing apparatus as set forth in claim 1, further comprising
a corner connecting structure, including:
bracing beams that are disposed in rows at a predetermined interval so as to
support each corner during underground pit excavation work; and
at least one connecting plate that is integrally coupled to any one of upper and
lower surfaces of each bracing beam by a coupling means so as to interconnect
the bracing beams.
[12] The temporary soil sheathing apparatus as set forth in claim 11, further
comprising at least one stiffener that protrudes outwards from one surface of the
connecting plate in a longitudinal direction.
[13] The temporary soil sheathing apparatus as set forth in claim 11, wherein the
coupling means includes:
a plurality of through-holes provided to each bracing beam and the connecting
plate;
bolts passing through the through holes; and
nuts screwed onto the bolts.
[14] The temporary soil sheathing apparatus as set forth in claim 11, wherein the
connecting plate has a quadrilateral shape, is plural in number, and is in a stacked
arrangement.

A temporary soil sheathing apparatus supports a set of intermediate bracing beams
in a triangular supporting structure during pit excavation work for constructing an
underground structure, so that it can satisfactorily support soil pressure. Thus, it is
possible to prevent space from being reduced by a complicated supporting structure,
reduce construction costs through reduced use of materials, and increase work space
to improve productivity. The temporary soil sheathing apparatus simplifies a corner
connecting structure, and reinforces ability to withstand the soil pressure transmitted
from the bracing beams and wales. Thereby, it is possible to prevent space from
being reduced by a complicated supporting structure, reduce construction costs
through reduced use of materials, and increase work space to thus improve
productivity.

Documents:

02389-kolnp-2008-abstract.pdf

02389-kolnp-2008-claims.pdf

02389-kolnp-2008-correspondence others.pdf

02389-kolnp-2008-description complete.pdf

02389-kolnp-2008-drawings.pdf

02389-kolnp-2008-form 1.pdf

02389-kolnp-2008-form 2.pdf

02389-kolnp-2008-form 3.pdf

02389-kolnp-2008-form 5.pdf

02389-kolnp-2008-international publication.pdf

02389-kolnp-2008-international search report.pdf

2389-KOLNP-2008-(20-11-2013)-ANNEXURE TO FORM 3.pdf

2389-KOLNP-2008-(20-11-2013)-CLAIMS.pdf

2389-KOLNP-2008-(20-11-2013)-CORRESPONDENCE.pdf

2389-KOLNP-2008-(28-03-2014)-ABSTRACT.pdf

2389-KOLNP-2008-(28-03-2014)-CLAIMS.pdf

2389-KOLNP-2008-(28-03-2014)-CORRESPONDENCE.pdf

2389-KOLNP-2008-(28-03-2014)-DESCRIPTION (COMPLETE).pdf

2389-KOLNP-2008-(28-03-2014)-DRAWINGS.pdf

2389-KOLNP-2008-(28-03-2014)-ENGLISH TRANSLATION.pdf

2389-KOLNP-2008-(28-03-2014)-FORM-1.pdf

2389-KOLNP-2008-(28-03-2014)-FORM-2.pdf

2389-KOLNP-2008-(28-03-2014)-FORM-3.pdf

2389-KOLNP-2008-(28-03-2014)-FORM-5.pdf

2389-KOLNP-2008-(28-03-2014)-OTHERS.pdf

2389-KOLNP-2008-(28-03-2014)-PETITION UNDER RULE 137.pdf

2389-kolnp-2008-abstract.jpg

2389-kolnp-2008-form 18.pdf


Patent Number 262746
Indian Patent Application Number 2389/KOLNP/2008
PG Journal Number 37/2014
Publication Date 12-Sep-2014
Grant Date 10-Sep-2014
Date of Filing 13-Jun-2008
Name of Patentee SUPPORTEC CO. LTD.
Applicant Address 5F KOIN BLDG., 229-9 POI-DONG, GANGNAM-GU, SEOUL 135-964 (KR)
Inventors:
# Inventor's Name Inventor's Address
1 BAIK, SEUNG DEOK 303-605 HYUNDAI RIVERVILL APT., PUNGNAP-DONG, SONGPA-GU, SEOUL 138-919 (KR)
PCT International Classification Number E02D 17/04
PCT International Application Number PCT/KR2006/004801
PCT International Filing date 2006-11-15
PCT Conventions:
# PCT Application Number Date of Convention Priority Country
1 10-2005-0109711 2005-11-16 Republic of Korea
2 10-2005-0109712 2005-11-16 Republic of Korea
3 10-2005-0109710 2005-11-16 Republic of Korea